Anatomy of a Bankable Feasibility Study: What Lenders and Investors Actually Check

JULIZAR Advisory Team · · 4 min read

Feasibility study for a dedicated rail line in East Kalimantan

A feasibility study can conclude that a project is viable and still fail to secure funding. The difference is usually not the conclusion but the evidence behind it. A bankable feasibility study is one that a lender’s credit team or an investment committee can test line by line and still reach the same answer.

This guide sets out what those reviewers look for, based on how credit and investment decisions are structured. It is a checklist, not a template: every project needs its own analysis.

1. A clear question and a clear answer

Reviewers start with the conclusion. A bankable study states, in the first pages:

  • what is being proposed (capacity, location, phasing, total investment),
  • what decision the study supports (internal approval, debt financing, equity raising),
  • and a verdict: feasible, feasible subject to conditions, or not feasible.

A study that only describes the project, without committing to a conclusion, forces the reader to do the analysis themselves. Most will not.

2. Demand that is measured, not assumed

Revenue drives every other number in the model, so it receives the most scrutiny. Reviewers ask:

  • Where does the demand forecast come from? Primary data (surveys, interviews with buyers, tenants or offtakers) carries more weight than desk research alone.
  • Who are the competitors, and what happens when they respond? A forecast that ignores existing and planned supply is a warning sign.
  • Is the ramp-up realistic? Occupancy, utilisation or sales rarely reach steady state in year one.

3. Costs that can be traced

CAPEX is the second most common reason for rejection. A credible cost estimate:

  • is built from quantities and unit rates, not a single lump sum,
  • separates hard costs, soft costs, land, financing costs and contingency,
  • states the design stage it relies on, with a contingency that matches the level of design completed.

Operating costs deserve the same treatment: staffing, utilities, maintenance, insurance and taxes, each with its source.

In Indonesia, a technically sound project can still stall on permits. Reviewers expect the study to confirm, or flag as a condition:

  • land status and title,
  • conformity with the spatial plan (RTRW/RDTR) and building parameters such as coverage and floor area ratio,
  • the business licences required for the sector, and the building approval (PBG) and certificate of occupancy (SLF) path,
  • environmental document requirements (AMDAL or UKL-UPL).

5. The financial metrics, read together

No single indicator makes a project bankable. Reviewers read them as a set:

MetricWhat it answersWhat reviewers check
NPVDoes the project create value at the required return?The discount rate used and how it was derived
IRRWhat return does the project generate?Comparison with the cost of capital or hurdle rate; equity IRR versus project IRR
Payback periodHow long until the investment is recovered?Sensitivity to delays in ramp-up
DSCRCan operating cash flow service the debt each year?The minimum year, not only the average. Lenders set their own minimum, often a ratio comfortably above 1.0x

The model itself should be handed over, unlocked, so the reviewer can change assumptions and see the effect.

6. Sensitivity and downside scenarios

Every forecast will be wrong to some degree. What matters is whether the project survives when it is. A bankable study shows:

  • the effect of lower revenue, higher CAPEX, construction delay and higher interest rates on NPV, IRR and DSCR,
  • the break-even point for the most important variable,
  • and a downside case that the sponsor and lender can live with.

7. Red flags that slow approval

From a reviewer’s point of view, these are the most common problems:

  • revenue growth that outpaces any plausible market growth,
  • contingency set at zero or left unexplained,
  • financing costs and working capital missing from the funding requirement,
  • conclusions that do not match the numbers in the model,
  • permits treated as a formality.

Where JULIZAR fits

JULIZAR prepares independent feasibility studies for projects in Indonesia, supported by our own market research and quantity surveying so that demand and cost assumptions are traceable. Reports are available in English and Indonesian. If you are preparing a project for financing, request a proposal and we will reply within one business day.

Share: WhatsApp LinkedIn X

Independent advisory

Make your next investment decision on evidence

Tell us about your project. We reply within one business day with a proposed scope, methodology and timeline. Initial consultation is free.

Start a conversation

Request a proposal

Share a short brief. Our consultants review every enquiry and reply within one business day with initial questions, a proposed scope and next steps.

  • Initial consultation free of charge, by video call or in person
  • Written proposal with scope, methodology, timeline and fee
  • Confidentiality covered by an NDA on request
Prefer to write directly? hallo@julizar.com
Or message us on WhatsApp.

Submitting opens your email application with the details filled in. See our privacy policy.

Related articles